Modular well-head geothermal power plant
Verkís has assisted Green Energy Geothermal, the solution provider, in developing modular and cost efficient well-head power plants since 2009.
Projects
Verkís has assisted Green Energy Geothermal, the solution provider, in developing modular and cost efficient well-head power plants since 2009.
Green Energy Geothermal (GEG) is a company focused on delivering turn-key flash type modular wellhead geothermal power plants on a turn-key basis. The concept is based on a power plant system prefabricated in ready modules that can be commissioned on site in a matter of weeks. Verkís has provided consulting services to GEG to develop the power plants which sizing ranges from 2,5 MWe to 6,4 MW.
By mid-2015, GEG had successfully commissioned 8 power plants totaling 45,6 MW in Olkaria, Kenya. The well head modular plant concept was initially designed to be installed at the first wells drilled at a geothermal field to produce electricity during construction of a larger power plant. This option allows developers to get a return on investment sooner than in conventional development schemes as the wellhead unit can be installed in a matter of months, rather than waiting years before it can be connected to a larger power plant. The well head units are designed to be moved between places, such as on to other wellheads as construction develops and wells are connected to larger power plant but can also be installed as permanent units.
The control/turbines/modules are designed to fit into standard 40ft ISO containers. The modules consist of multistage steam turbines with hydraulically operated governing valves for inlet steam flow control, 3 Phase, 50/60 Hz synchronous AC generator, advanced direct contact condenser, two stage steam ejector system with intercooler and a counter current flow cooling tower with mechanically induced draft.
Verkís has contributed to the development and design of the concept and supported the GEG research and development team on various specific aspects.
Installed Capacity
Wellhead Power Plants
Modular Units
Traditional geothermal power plant developments often require significant upfront investment and several years before electricity generation can begin. The challenge was to develop a flexible, cost-effective solution that enables developers to generate power from individual wells much earlier in the project lifecycle.
Verkís has supported Green Energy Geothermal (GEG) in the development of modular wellhead geothermal power plants since 2009. Our engineering expertise contributed to the design and optimization of prefabricated, containerized power plant modules ranging from 2.5 MW to 6.4 MW, helping create a standardized solution that can be rapidly installed, relocated and integrated into larger geothermal developments.
The modular wellhead concept has successfully demonstrated its value in accelerating geothermal development, with eight power plants totaling 45.6 MW commissioned in Kenya. By enabling electricity production within weeks rather than years, the solution provides earlier returns on investment, greater project flexibility and a scalable approach to expanding geothermal energy production worldwide.
Technical information
Location:
Olkari, Turkey
Size:
2.5 – 6.4 megawatts
Project period:
2009 –
Discover how we helped clients solve complex technical, environmental, and operational challenges through innovative engineering and strategic consulting across global energy markets.